Civic Center’s foundation begins

Bank to negotiate Spruce Street purchase with city

Crews pour the first concrete in the early morning on July 30 at the new Sequim Civic Center. This week

The first slab of concrete is down for the City of Sequim’s Civic Center.

Crews with Lydig Construction began pouring the first floor foundation on July 30 for the east side of the building.

Court Olson, project manager for the city, told Sequim City councilors July 28 that everything is on time and budget so far for the joint city hall and police station.

“We’ve passed the most at risk portion of the project (to use contingency funds),” he said.

“It’ll be highly unusual for us not to finish on budget.”

City Manager Steve Burkett said the city has budgeted $12.1 million this year for the project and has spent $2,339,000 so far. Burkett’s total project budget from Jan. 1, 2014, through the end of the project in mid-2015 is $13,810,661.

Olson said the first floor should be in place by the end of August and residents should see a steel structure going up soon thereafter with a roof on hopefully before the rainy season.

Last week, Lydig’s crews installed irrigation sleeving and underground infrastructure while the Clallam PUD worked to relocate power poles.

This week both crews will continue their work and prepare the west side of the building for the remainder of the concrete slab.

Eminent domain update

Burkett told city councilors at the July 28 meeting that city staffers remain “somewhat optimistic” that the bank will allow the sale to go through on an adjacent property at 191 W. Spruce St. to the new civic center for parking.

On July 14, City Attorney Craig Ritchie reported the bank of homeowners Steven and Peggy Sutherland of Renton requested a settlement.

Burkett told the Gazette last week that the city has “received the appraisal on that house and it came in at $92,000 so we are hopeful that we can settle with the bank somewhere between $90,000 and $92,000.”

City councilors voted unanimously on June 9 to enforce a short sale on the property, which Ritchie said came two years after the sale was agreed upon.

He added that the bank loaned the Sutherlands more ($140,000) than what the city is buying it for now, which likely was holding up the sale.

City staff indicated that if the house is not obtained by the end of the year it could delay the civic center project and cost more than anticipated to bring back the subcontractors for demolition and construction.

If the sale goes through, the city requests “immediate use and possession” of the property.

For more updates on the civic center project, visit www.sequimwa.gov.


 

More in News

Primary Election: Incumbents post strong numbers in initial ballot counts

Each of the three incumbents in Legislative District 24 posted strong numbers… Continue reading

Sequim schools set staged opening for September

With administrators and local health leaders seeking a hybrid model to open… Continue reading

Police blotter — Aug. 5, 2020

The weekly police blotter includes incidents that occurred in the City of… Continue reading

Dr. Allison Unthank was appointed as Clallam County’s public health officer in September 2018. Submitted photo
Clallam’s health officer faces pandemic with empathy, facts

Since she was 11, Dr. Allison Berry Unthank knew she was meant… Continue reading

VHOCC to host in-person volunteer orientation

Volunteer Hospice of Clallam County (VHOCC), a local nonprofit that serves communities… Continue reading

Sequim city councilors agreed in late July to extend a moratorium for six months on manufactured home developments so city staff and the planning commission could better analyze the Sequim Municipal Code’s language on private streets. Discussions about private streets in manufactured home developments came up late last year during the binding site plan application for Lavender Meadows, a 217-site manufactured home park at the intersection of North Sequim Avenue and Port Williams Road. It was approved earlier this year. Sequim Gazette photo by Matthew Nash
City extends moratorium on manufactured homes

Two temporary positions added for increased services need

Employees at Sequim Costco helped save a woman with a defibrillator on Aug. 1 after she fainted outside the business. Sequim Gazette photo by Matthew Nash
Costco employees save woman with defibrillator

Fire District commends live-saving efforts

Autrey, Olympic Medical Center clinic manager, lauded for COIVD-19 response

Aleisha Autrey, Olympic Medical Center’s walk-in clinics manager, was presented a leadership… Continue reading

Library system seeking feedback for programs, services

The North Olympic Library System (NOLS) is looking for feedback to help… Continue reading

Most Read